**Detailed explanation of installation steps for Roots blower (Professional Engineer Edition)**
	---

	**1、 Preparation before installation**
	1. * * Basic acceptance**
	-Concrete strength ≥ C25, flatness deviation ≤ 2mm/m2
	-Position error of pre embedded anchor bolts ± 3mm (it is recommended to use elastic shock-absorbing pads)
	-Reserved maintenance space: ≥ 800mm on both sides, ≥ 1000mm on the top
	2. * * Unpacking inspection**
	-Check the nameplate parameters (flow rate/pressure/speed)
	-Check the flexibility of rotor rotation (no jamming during manual turning)
	-Confirm that the attachments are complete (couplings, anchor bolts, instructions, etc.)
	---
	**2、 Mechanical installation process**
	1. * * Host in place**
	-Use forklifts or lifting equipment (with lifting points located on dedicated lifting lugs)
	-After initial leveling, the anchor bolts are temporarily not tightened (leaving a 0.5mm adjustment allowance)
	2. * * Horizontal calibration**
	-Measure on the machined surface of the bearing seat, with a levelness of ≤ 0.05mm/m
	-Use a precision level (accuracy 0.02mm/m)
	3. * * Coupling/Belt Installation**
	|* * Transmission type * * | * * Technical requirements * *|
	|--------------|------------------------------|
	|Direct connection | Radial deviation ≤ 0.05mm, angular deviation ≤ 0.02mm|
	|Belt drive | Belt tension: press down with thumb to sink 10-15mm|
	4. * * Import and export pipeline connection**
	-Add asbestos rubber pad (thickness 3mm) between flanges
	-The pipeline needs to be independently supported (fan bearing is prohibited)
	-The distance between the elbow and the inlet is ≥ 2 times the pipe diameter (to reduce turbulence)
	---
	**3、 Key points of electrical installation**
	1. * * Motor wiring**
	-380V three-phase motor insulation resistance ≥ 1M Ω (tested with a 500V megohmmeter)
	-Steering confirmation: jog test consistent with the arrow on the shell
	2. * * Control System**
	-Variable frequency drive parameter setting (startup time ≥ 30 seconds)
	-The overload protection value is set to the rated current of 110
	---
	**4、 Installation of auxiliary systems**
	1. Lubrication system**
	-Inject ISO VG220 gear oil into the gearbox to the centerline of the oil gauge
	-The bearings are lubricated with lithium grease (with a grease injection volume of 60% of the cavity)
	2. * * Cooling system**
	-Water cooled machine model pressure test 0.4MPa, hold for 30 minutes without leakage
	-Air cooled models ensure unobstructed heat dissipation fins
	3. * * Device**
	-Valve popping pressure ≤ 1.1 times rated pressure
	-The range of the pressure sensor covers 1.5 times the working pressure
	---
	**5、 Debugging and running steps**
	1. * * No load test run**
	-Remove the coupling/belt and test the motor for 30 minutes
	-Test vibration value (≤ 4.5mm/s at the bearing)
	2. * * Load trial operation**
	|* * Stage * * | * * Operational Requirements * * | * * Acceptance Criteria * *|
	|------------|------------------------------|-------------------------|
	|0-30 minutes | 25 load operation | Bearing temperature rise ≤ 40 ℃/h|
	|30-60 minutes | 50 load operation | Current fluctuation ≤ 5 rated value|
	|1-2 hours | Load operation | No leakage at each flange interface|
	3. * * Performance testing**
	-Flow deviation ≤± 5 (detected by orifice flowmeter)
	-Noise test (≤ 85dB (A) at a distance of 1m from the equipment)
	---
	**6、 List of Acceptance Documents**
	1. Observation records of foundation settlement (continuous for 7 days)
	2. Vibration detection report (including spectrum analysis)
	3. Trial operation data record table (hourly record)
	4. Lubricating oil testing report (particle size NAS level 8)
	---
	**7、 Professional precautions**
	1. Explosion proof places**
	-Use copper tools (to avoid sparks)
	-The junction box must comply with the Ex d Ⅱ CT4 standard
	2. High temperature medium**
	-Expansion joints are installed in the import and export pipelines (compensation amount ≥ 5mm)
	-At least 3 temperature measurement points on the shell (top/sides)
	3. * * Special materials**
	-Stainless steel fans need to be pickled and passivated after welding
	-Titanium alloy rotors are prohibited from coming into contact with chlorine containing cleaning agents
	---
	**Attachment: Installation Deviation Control Table**
	|* * Project * * | * * Allowable Deviation * * | * * Testing Tool * *|
	|----------------|----------------|-------------------|
	|Levelness | ≤ 0.05mm/m | Electronic level|
	|Coupling alignment | ≤ 0.03mm | dial gauge+alignment frame|
	|Pipeline stress | ≤ 0.1mm/m | Laser collimator|
	According to this specification, installation can ensure that the operating life of the equipment is ≥ 10 years, and the first major overhaul cycle is extended by 30 years. Suggest saving the installation process image data for future reference.

          
          
          
          